A first article inspection (FAI) gives the buyer a documented basis for reviewing a part made with the intended production process. On a custom CNC order, the most useful report ties each required check to the approved drawing, identifies the part inspected, and shows what the supplier actually found.

Agree on the evidence before placing the order

Send the current drawing and CAD model, and state which controls if the two differ. Identify the part number, revision, material, finish, and any separate specifications. Agree whether the inspection covers every drawing characteristic or a defined subset, how many parts to inspect, and whether written approval is required before the balance of the order proceeds.

If the first run uses multiple fixtures, machines, or process routes, discuss whether each route needs its own sample. A prototype made with a different setup can answer design questions, while evidence for production release should reflect the process agreed for that order.

What belongs in the inspection report?

  • Part identity and traceability. Record the part and revision, purchase order, inspected sample identifier, and applicable material or processing lot references.
  • A drawing reference for each check. Use numbered callouts on a copy of the drawing and match each number to the report. Capture relevant drawing notes as well as dimensions.
  • Requirement, result, and method. Include the units and limits, the measured value where the requirement calls for a numerical result, and the method used. For an attribute check such as a GO/NO-GO gauge, record the result and identify the gauge as agreed.
  • Supporting evidence. Link material certificates, finish reports, or other documents when the purchase order requires them. If a feature must be inspected before finishing, identify that inspection stage.
  • Exceptions and disposition. Keep out-of-tolerance results visible and record who can approve a deviation or decide that a corrected sample is needed.

Example: A machined mounting flange

Suppose a flange has a locating bore and four mounting holes. Record the bore size separately from the hole pattern position. For position, agree on the drawing datums and how the part will be located during inspection. If a coating is required, confirm which dimensions apply in the finished condition and whether any areas must be masked. Attach the finish evidence to the same sample or lot record so the reviewer can trace it.

When should inspection be repeated?

Agree before production how a drawing revision, changed manufacturing location, or a change in tooling or finish will be evaluated. A targeted inspection may be enough when the affected characteristics are clear and the purchase requirements allow it. Use the governing contract or standard to decide when a full inspection is required. For projects that specify an aerospace FAI framework, see the IAQG 9102 overview and apply the revision required by the order.

Common buyer questions

Does first article approval release every future shipment? First article approval applies to the agreed release decision. Set ongoing inspection, sampling, and shipment documentation separately in the purchase requirements.

Can a certificate replace measured results? A certificate may support material or process conformity. Provide measured results separately wherever the inspection plan requires dimensional evidence.

For related guidance, see our drawing revision control guide and thread gauging guide.

Request a quote for custom CNC parts

Send CPRMFG your 2D drawing and 3D model, material and finish, estimated quantities, and any first article or final inspection requirements. Email CPRMFG for a quotation and inspection plan review.

Cover illustration: coordinate measurement of a representative CNC-machined flange.